Updating the storage format
This dialog appears when updating the compiler version of the project. After saving the project with the new save format, it can no longer be opened with an old PLC Designer.
If you click <No> and you save the project with the PLC Designer V4, you can open the project with the PLC Designer V3, but not without errors. The placeholder resolution of libraries is done in the PLC Designer V4 with the Lenze FAST profile. This is not known to the PLC Designer V3 and causes errors.
Update the storage format