Start/stop/abort tracking
Start tracking
The FB is started by a rising edge at the Execute input. The FB itself does not command any movement, but is only responsible for calculating the dynamic product coordinate system (PCS).
- Synchronization only takes place when a motion-applying FB (e.g. MC_MoveLinearAbsolute , MC_MoveLinearRelative) is called up in the same PCS as the MC_TrackConveyorBelt.
- Coupling modes and prioritizations
- The ClutchTime input parameterises a time-controlled clutching and is used when the ClutchDistance input is assigned with zero.
- The ClutchDistance input parameterises a path-controlled clutching and has priority over the ClutchTime input.
- If both inputs are parameterised, an error is output.
- If both inputs are parameterised to non-zero, ClutchDistance is used
- Behaviour in case of abortion
- The declutch process always uses the time entered at the ClutchTimeAbort output if the active tracking was aborted before via the Abort input.
- If the kinematics moves synchronously to the belt conveyor, the InSync output is set to TRUE.
- The starting performance depends on the configuration of the SetDynPCS input:
- SetDynPCS = TRUE (default): With a rising edge at the Execute input, the calculation of the dynamic PCS starts immediately.
-
SetDynPCS
= FALSE: With a rising edge at the
Execute
input, the calculation is only prepared (the current belt position is saved). Only when the
SetDynPCS
input is set to TRUE, the calculation of the dynamic PCS starts.
Delayed setting of the PCS
- The DynPCSSet output shows that a dynamic PCS is calculated and the FB is ready to synchronise an instructed motion.
- The Active output is set if the FB transmits overlapping values to the axes group, which means that a synchronisation is active.
Stop tracking
Tracking is stopped if a motion-instructing FB is executed together with a different PCS than the dynamic one used. If afterwards a motion is instructed again in the dynamic PCS, it is synchronised again.
When the synchronised motion is decoupled, the following applies (according to clutch-in): The target point programmed in the motion-instructing FB is only reached if both the MC_TrackRotaryTable and the overriding FB set their Done outputs.
|
Note!
If the Execute input is set during or before a synchronisation to FALSE, the synchronisation is executed anyway. |
Abort tracking
The following options are available to abort the tracking:
- Activating the Abort input
- Writing access to the selected PCS by another FB (e.g. MC_SetCoordinateTransform )
|
Note!
The active tracking can only be aborted if
If the PCS is still tried to be accessed,
|