Commissioning

The EtherCAT master enables the control of the subordinate EtherCAT device. Connected EtherCAT slaves can be configured in this way using the engineering PC.
 
Preconditions
–
The field devices are installed as per the information in the device-specific mounting instructions.
 
–
The commissioning of the controller is completed.
 
 
Recommended sequence of the commissioning steps
1.
Use the Online Login menu command or the <Alt> + <F11> keys to log into the controller.
 
2.
 
3.
Adapt the network configuration.
 
4.
 
5.
Use the Build Compile menu command or the <F11> function key to compile the program code.
 
6.
Use the Online Login menu command or the <Alt> + <F11> keys to load the configuration.
 
7.
Use the Debug Start menu command or the <F5> function key to start the PLC program.