Commissioning

In the following chapters, the steps required for controlling the inverter with a IO-Controller via PROFINET are described.
 
Preconditions
–
As an IO-Device, the inverter is connected to an IO-Controller and further PROFINET nodes if required.
See "Typical topologies" under: PROFINET 
 
–
The entire wiring has been checked for completeness, short circuit and earth fault.
 
–
All PROFINET devices are supplied with voltage and are switched on.
 
–
The functional test described in the mounting and switch-on instructions has been completed successfully (without any errors or faults).
 
–
The inverter is commissioned with the »EASY Starter«.
 
 
–
The IO-Controller is commissioned with a different engineering tool, e. g. Siemens »TIA Portal«.
For this purpose, install the required GSDML device description file in the engineering tool for the IO-Controller for configuring the inverter.
We always recommend the use of the current device description.
 
–
 
–
Please observe the necessary system requirements and the notes regarding the inverter.
 
Device description file 
 
 
A firmware download from the PLC to the inverter via the network only takes place under the following conditions:
• Required firmware version 05.01.x.x or higher
• Bootloader version 00.00.00.18 or higher
 
 
Settings in the »EASY Starter«
1.
Activate network control: 0x2631:037 (P400.37) = "TRUE [1]"
 
2.
Set network as standard setpoint source: 0x2860:001 (P201.01) = "Network [5]"
In the default setting, the digital input DI1 is assigned the "Run" function. If the network control is activated, this function serves as "start enable" for start commands via network. Hence, the digital input DI1 must be set to the HIGH level in order that the motor can be started via the network.
 
 
3.
Set the IP address and the station name ("PROFINET device name").
See: Station name and IP configuration
 
4.
Adjust data mapping for process data.
Observe the information about data mapping and the example below:  
 
5.
Save the project in the engineering tool.
 
6.
Save the mapping and all other parameters in the inverter 0x2022:003 (P700.03) with mains failure protection.
See: Saving the parameter settings
 
 
Settings in the »Siemens TIA Portal«
Here, commissioning with the »Siemens TIA Portal« is described.
Please note that in the standard setting of the »Siemens TIA Portal« changes of network parameters carried out by a Lenze engineering tool (e. g. »EASY Starter«) may be overwritten.
 
1.
Go to the device configuration and open the "net view" to drag the inverter from the catalog to the net view of the PROFINET.
 
2.
Assign the inverter to the associated IO-Controller.
 
3.
Mark the inverter and change to the "device view".
 
4.
Set the IP address and the station name ("PROFINET device name") in "Properties".
In order that the inverter can be identified via Ethernet when the IO controller is switched off, it is necessary that the IP address is saved in the inverter with mains failure protection via the separate entry with the »EASY Starter«.
Use the 0x2022:003 (P700.03) parameter to save the settings. More information: Saving the parameter settings 
 
 
5.
Below the module name and the name of the device description file, the device view shows the pre-assignment of three output and input process data words:
 
–
Additional process data words can be added or pre-allocated process data words can be changed in the device view.
 
–
The length of the process data can be selected based on the GSDML device description file.
 
–
All addresses of the input and output data words must follow each other without interruption.
 
–
Observe the information about data mapping and the example below:  
 
 
6.
Save the project in the engineering tool.
 
7.
Load the configuration into the IO-Controller.
 
8.
Place the IO-Controller in "RUN", e. g. by setting bit 4 in the NetWordIN1 control word (0x400E:005 (P505.05)).
 
–
The start-up causes the current configuration to be transferred to the inverter.
 
–
If required, save mapping and all other parameters in the inverter with 0x2022:003 (P700.03) with mains failure protection, see Saving the parameter settings 
 
 
 
Restart or stop communication
The 0x2380 (P508.00) parameter can be used to restart or stop communication. Optionally it is also possible to reset all communication parameters to the default status.
A restart of communication is required after changes of the interface configuration (e. g. station address and baud rate) in order that the changed settings become effective.
For restarting communication, there are two options:
1.
Switch inverter off and on again.
 
2.
0x2380 (P508.00) Set = 1 (Restart with current values).