Restarting or stopping the communication Configuring the device as mini master
If the initialisation of the CANopen network and the associated status change from "Pre-Operational"
to "Operational" is not effected by a master (PLC), the inverter can instead
be defined as a "mini master” to execute
this task.
Details
In the default setting, the inverter is configured as a slave and waits for the NMT telegram "Start Remote Node" from the CANopen master (PLC) after being switched on in the "Pre-Operational" state.
If the initialization of the CANopen network and the associated change of state from "Pre-Operational" to "Operational" is not taken over by a higher-level CANopen master (PLC), an inverter must be configured as a mini-master.
Configured as mini master, the inverter changes to the "Operational" state after being switched on and sets all nodes connected to the CAN bus (broadcast telegram) to the "Operational" communication state using the "Start Remote Node" NMT telegram after the "Start remote delay time" has elapsed. Only this communication status enables data exchange via the process data objects.
–
Activate mini master:
0x2301:003 = [1]
0x2301:003 = [1]–
Delay time until the NMT telegram "Start Remote Node" is sent:
0x2301:004
0x2301:004Parameter
The change becomes effective only after saving the parameter set and restarting the communication.
Restarting or stopping the communication
Restarting or stopping the communication