Commissioning

In the following, the steps required for controlling the inverter via CANopen are described.
 
Required commissioning steps
How to set up the controller via CANopen:
Required settings:
1.
Activate bus terminating resistor at the physically first and last node in the network. Activating the bus terminating resistor 
 
2.
Set the CANopen node setting. Node address setting 
Each network node must be provided with a unique node address.
 
3.
Set CANopen baud rate. Baud rate setting 
Default setting: 500 = kbps
 
4.
 
5.
Select technology application: 0x4000 > 1.
 
6.
Select interface: 0x4001 = [0] Fieldbus network.
 
 
Optional settings
1.
Configure inverter as “mini master”. Configuring the device as mini master 
Required if the initialization of the CANopen network and the associated status change from "Pre-Operational" to "Operational" is not effected by a higher-level CANopen master (PLC).
 
2.
Change response of the inverter when RPDO time monitoring is triggered. Error responses 
Default setting: In case of missing RPDOs, an error is triggered.
 
 
Final settings
1.
Save parameter settings: 0x2022:003 = = [1] On / start.
 
2.
 
 
The inverter can now be controlled via CANopen.