Set voltage boost
As an alternative for the “Activate voltage vector control (Imin controller)“ function, a constant, load-independent voltage boost can be specified for low speeds (below the V/f rated frequency) or for a motor standstill in order to optimize the starting performance.
WARNING!Insufficient cooling of the motor due to longer operation at standstill.
If the motor is operated at standstill for a longer time - especially in case of smaller motors - the motor can be destroyed by overtemperature!
▶
Connect the PTC thermistor (single sensor according to DIN 44081 or triple sensor according to DIN 44082) or thermal contact (normally-closed contact)
Motor temperature monitoring.
Motor temperature monitoring. ▶
Parameterise and activate the
Motor overload monitoring (i²xt).
Motor overload monitoring (i²xt). NOTICE
The voltage boost is added to the function
Activate voltage vector control (Imin controller).
Activate voltage vector control (Imin controller). Only set one of the two "boost" functions.
Recommendation: voltage vector control
For magnetising the motor, consider a sufficient time from the controller enable to the start of the speed ramp function generator. The bigger the motor the longer the time required for magnetisation. A motor with a power of 90 kW requires up to 2 seconds.
Depending on the required starting torque, the voltage boost must be set so that the required motor current will be available after controller enable.
–
The voltage boost can be calculated by multiplying the stator resistance by the rated magnetising current:
–
Optionally, the voltage boost can be determined empirically by increasing the setting until the rated magnetising current flows.
–
The voltage boost is added geometrically to the voltage of the characteristic: