After installation, after each change to the safety configuration and after a device replacement, the user must test the safety configuration loaded into the inverter with user tests:
–
To test and verify the configuration of an originator with connection data, it must first be downloaded to the inverter. This is the only way to confirm the SCID of the inverter.
–
Check the signature of the safety configuration (SCID). Only then can the safety configuration be considered verified.
–
Check and prove the operability of the safety configuration used.
–
Test the configurations of the safety connections after they have been applied in the originator (safety master). Only then is it ensured that the target connection functions as intended.