The following commissioning instructions must be followed:
General instructions
-
As far as possible, avoid connecting the controller to open networks or the internet. We recommend organizational and technical actions for the controller.
-
For protection, additionally use data link layers such as a VPN for remote access.
-
Install Firewall mechanisms, IPS (Intrusion Prevention Systems) and IDS (Intrustion Detection Systems).
-
Connect external devices upstream to provide protection against DoS (Denial of Service) or DDoS (Distributed Denial of Service) attacks.
-
Restrict physical access to authorized persons only.
-
Change existing default passwords after the first start-up and regularly afterwards. Please use only high-strength passwords.
-
As soon as the web server functions of the Controller are accessed with a browser, we recommend activating the logging functions of the browser and backing up the certificate store of the browser. In this way, communication to the controller can be traced.
Commissioning and hardening instructions
-
Change the key for SFTP server communication (Controller.SFTPServer).
-
Be sure, that there is no ".enable-ssh" file on the SD card for SSH access (Controller.SSHServer).
-
Change the settings of the controller firewall for hardening the component (Controller.Firewall).
-
Activate and use the user management (Controller.UserManagement).
-
Change the standard EngineeringItf-User-Password (Controller.UserManagement: EngineeringItf) or delete this standard user.
-
Prevent the deletion of the user management on the SD card via an organizational measure (Controller.UserManagement).
-
Activate the function "Encrypted Communication" (Controller.EncryptedCommunication.PLCDesigner).
-
Activate encrypted application to secure the application on the controller (Controller.Application.Encryption).
-
Handle the certificates in the programming phase of the machine with the »PLC Designer« (Controller.CertificateStore.viaPLCDesigner).
-
Handle the certificates in the production phase via the Diagnosis Visu (Controller.CertificateStore.viaAdvancedVisu).
-
Change the credentials for the WebDiagnosis Controller.WebDiagnosis).
-
Change the communication to the web visualization to https (Controller.CertificateStore.HAProxy).
-
When using the OPC-UA Server, please use the authentication (Controller.OPCUAServer.Authentification) and the certificate handling (Controller.OPCUAServer.Certificate).
-
When using the OPC-UA Client, please use the Authentication Controller.OPCUAClient.Authentificate) and the certificate handling (Controller.OPCUAClient.Certificate).
-
Activate and test the component directory at the controller (Controller.ComponentDirectory).
-
Activation and configuration of the NTP client (Controller.NTP).
-
When using the WebVisu in the extended controller variant, please harden the communication and the web server (Controller.WebVisu.Activation) and the (Controller.WebVisu.Certificate) and the (Controller.WebVisu.UserManagement)
-
Activate the SysLog functionality for logging security relevant events (Controller.SysLog).
-
Do not activate the USB stick functionality. This will deactivate the security functionality.
-
When setting the USB stick parameter to “once for a restore/update” make sure that the functionality is used immediately.
Periodic security maintenance
-
It is recommended to check the password policy periodically for updates and to adjust the requirements if necessary.
-
It is recommended to change the passwords cyclically.
-
It is recommended to check the certificates used with regard to their key lengths for up-to-dateness and to generate new certificates with higher key lengths if necessary.
-
It is recommended to exchange the certificates regularly.
Decommissioning instructions
-
The device command 0x2022:001 "Device command: Load Lenze settings" must be executed. This resets all application settings.
-
It is recommended to update the firmware using the EASY Firmware Loader.
-
Remove the SD card and format it (in order to retain the Application Credits, the corresponding data must first be memorized and restored on the formatted SD card).
Removal product from environment
-
It is recommended that all industrial communication partners of the controller to be removed, to change the trusted certificates of the controller into untrusted certificates.
-