The following commissioning instructions must be followed:

General instructions

  • As far as possible, avoid connecting the controller to open networks or the internet. We recommend organizational and technical actions for the controller.

  • For protection, additionally use data link layers such as a VPN for remote access.

  • Install Firewall mechanisms, IPS (Intrusion Prevention Systems) and IDS (Intrustion Detection Systems).

  • Connect external devices upstream to provide protection against DoS (Denial of Service) or DDoS (Distributed Denial of Service) attacks.

  • Restrict physical access to authorized persons only.

  • Change existing default passwords after the first start-up and regularly afterwards. Please use only high-strength passwords.

  • As soon as the web server functions of the Controller are accessed with a browser, we recommend activating the logging functions of the browser and backing up the certificate store of the browser. In this way, communication to the controller can be traced.

Commissioning and hardening instructions

Periodic security maintenance

  • It is recommended to check the password policy periodically for updates and to adjust the requirements if necessary.

  • It is recommended to change the passwords cyclically.

  • It is recommended to check the certificates used with regard to their key lengths for up-to-dateness and to generate new certificates with higher key lengths if necessary.

  • It is recommended to exchange the certificates regularly.

Decommissioning instructions

  • The device command 0x2022:001 "Device command: Load Lenze settings" must be executed. This resets all application settings.

  • It is recommended to update the firmware using the EASY Firmware Loader.

  • Remove the SD card and format it (in order to retain the Application Credits, the corresponding data must first be memorized and restored on the formatted SD card).

Removal product from environment

  • It is recommended that all industrial communication partners of the controller to be removed, to change the trusted certificates of the controller into untrusted certificates.

  • It is recommended to securely remove the login data for the controller to be removed,and such as name and password for the necessary authentication, from all industrial communication partners.